Name
Pembangkit Listrik Tenaga Uap (PLTU) Batang Ultra Super Critical Coal-fired Power Plant
Contractor
Mitsui Engineering & Shipbuilding
Constrution year
2017
Address
Batang, Central Java, Indonesia
Bonna Indonesia to supply PLTU Batang 2,000-MW power plant, Indonesia's biggest power plant
PLTU Batang or Central Java Power Plant (CJPP), Central Java, Indonesia, is a 2x1,000-megawatt ultra super critical coal-fired power plant which has been billed as the largest project of its kind in Indonesia.
Bonna Indonesia has provided provide 1,300 pressure pipes each measuring 3.2 meters in diameter, or the equivalent of 23,000 tonnes of concrete; 1,550 spools; and 250 special fittings. Production time will span 70 weeks.
Owner: Bhimasena Power
EPC: Mitsui Engineering & Shipbuilding
RCCP Installer: SSP
Bonna Indonesia's scope: Onshore CW System, RCCP pipes & special fittings
Total Length: 3266 meters
Diameter: ND3200 mm
Pressure: MWP 4 bar